You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting milestone tasks. (Choose three.)
A. only one labor resource assignment with 100 effort
B. lowest-level tasks set up with non-zero duration
C. lowest-level tasks set up with zero duration
D. only one labor resource assignment with 0 effort
E. percent work complete values of 0 or 100 percent
Identify the attribute of a project type that determines if expenditure items are billable , and the amount type to be used as the basis for transfer pricing. (Choose the best answer.)
A. work type
B. event type
C. cost type
D. expenditure type
Your customer has separate organizations to maintain indirect, capital, and billing types of projects. Identify the two setups that can be used to fulfill this requirement. (Choose two.)
A. Project Type
B. Business Unit
C. Project Organization Classification
D. Organization Tree
E. Project Accounting Business Function
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand. (Choose two.)
A. Labor Demand FTE is calculated as Quarterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.
B. Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.
C. Labor Demand FTE is calculated as Project Allocation hours divided by Project FTE hours, if project duration is used as the basis for viewing labor demand.
D. Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.
You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)
A. Exceptions
B. Accounting Calendar
C. Workday Patterns
D. Time Off
E. Expenditure Type
As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the burden schedule override at a task level, which was done during the second month of the quarter.
What is the reason for this problem?
A. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier cannot be reprocessed.
B. Only new expenditure items charged to the task use the new burden schedule; expenditure items processed earlier can be manually marked for reprocessing.
C. You can enable automatic reprocessing of expenditure items processed before the burden schedule change.
D. All expenditure items charged to the task use the new burden schedule.
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
A. Effort
B. Cost
C. Manual Entry
D. Remaining Plan
Your customer wants a team member who is assigned to a project to be able to create and submit a forecast, but not to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? ( Choose the best answer.)
A. Project Manager
B. Project Administrator
C. Project Application Administrator
D. Project Accountant
Which three are valid password complexity criteria while setting up password policies? (Choose three.)
A. Complex: At least 8 characters, 1 uppercase, and 1 number
B. Very Complex: At least 8 characters, 1 uppercase, 1 number, and 2 special characters
C. Very Complex: At least 6 characters, 1 uppercase, 1 number, and 1 special character
D. Very Complex: At least 8 characters, 1 uppercase, 1 number, and 1 special character
E. Simple: At least 8 characters and 1 number
You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: "The search for resources cannot be completed because the project resource search index is not available. Contact your help desk."
Identify the cause for this error message. (Choose the best answer.)
A. The index is not in the process.
B. The index has been built.
C. The index is in the process of being updated.
D. The most recent update of the index finished successfully.