Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > Oracle > Oracle Certifications > 1Z0-466 > 1Z0-466 Online Practice Questions and Answers

1Z0-466 Online Practice Questions and Answers

Questions 4

Which Oracle Unified Method phase includes Bid Transition?

A. Project Start Up

B. Project Closure

C. Project Executing and Control

D. Financial Management

Buy Now

Correct Answer: A

Questions 5

What is true about planning a project in OUM Manage?

A. All tasks are executed to the same degree during the Project Execution and Control phase.

B. There is no distinction between executing and controlling the project and executing and controlling an iteration/phase.

C. The project plan that is established in the Project Startup phase details each task through the end of the project.

D. Manage tasks are not included in the project work plan.

Buy Now

Correct Answer: B

Note: Iterative and Incremental OUM recognizes the advantages of an iterative and incremental approach to development and deployment of information systems. Any of the tasks within OUM may be iterated. Whether or not to iterate, as well as the number of iterations, varies. Tasks may be iterated to increase quality of the work products to a desired level, to add sufficient level of detail, or to refine and expand the work products on the basis of user feedback

Questions 6

Select the three applicable goals of the OUM Manage Focus Area.

A. Identify and communicate with project stakeholders.

B. Effectively transition from the sales (bid) process to Project Start Up

C. Manage to reduce overall project risk.

D. Define scope of work.

E. Decreases implementation time.

F. Create better project plans.

Buy Now

Correct Answer: ABD

/The Manage focus area is organized into 13 processes: (B)Bid Transition (D)Scope Management Financial Management Work Management Risk Management Issue and Problem Management Staff Management (A)Communication Management Quality Management Configuration Management Infrastructure Management Procurement Management Organizational Change Management

/OUM Manage Focus Area

Questions 7

Earned value is a technique to report project status using which three variables?

A. EV ?Earned Value

B. PV ?Planned Value

C. AC ?Actual Cost

D. PC ?Planned Cost

E. EC ?Earned Cost

Buy Now

Correct Answer: ABC

EV -earned value, estimated value of work done. PV -planned value, estimated value of planned work AC -actual cost, what you paid

Questions 8

What does OUM Manage recommend for stakeholder involvement?

A. the project sponsor is the only stakeholder involved in Bid Transition

B. the steering committee is formed during Project Execution and Control

C. stakeholders be engaged early in the project

D. only internal stakeholders should identify risks and issues

E. work products are reviewed by all stakeholders identified in the contract

Buy Now

Correct Answer: C

Note: *Where is Stakeholder Management in OUM? Stakeholder Management typically falls into the purview of the Project Manager, which means much of the associated guidance is found in the OUM Manage Focus Area (a.k.a. Manage). There is also a good deal of content related to the discipline of Stakeholder Management contained in the Implement Focus Area (a.k.a Implement).

There is no process in Manage named Stakeholder Management, but this "touch point" can be found in a variety of other processes including Bid Transition (BT), Communication Management (CMM) and Organizational Change Management (OCHM).

?Stakeholder Management starts in the Bid Transition process with Stakeholder Analysis.

?This Stakeholder Analysis is used to build the Project Team Communication Plan in the Communication Management process.

?Stakeholder Management should be executed during the Execution and Control phase. For example, as issues are resolved, the project manager should take the action item to follow up with the affected stakeholders to ensure they are aware that the issue has been resolved.

?The broader topic of Stakeholder Management is also addressed very thoroughly in the Organizational Change Management process in the Implement Focus Area, which is a touch point to the Organizational Change Management process in Manage.

Questions 9

Which term means executing the systematic quality activities to determine if the quality processes are being followed and whether they are satisfying the project quality needs?

A. Quality Planning

B. Quality Control

C. Quality Assurance

D. Process Improvement

Buy Now

Correct Answer: B

Questions 10

Select the three major activities in the Project Start Up phase.

A. Develop Staff Plan and Budget

B. Manage Project Quality

C. Validate Scope, Stakeholders, and OCM Strategy

D. Review Bid and Contract

E. Establish Estimate

F. Develop DetailProject Plan

Buy Now

Correct Answer: ACD

*The Project Start Up phase precedes the Inception phase. Project startup is where all of the projectplanning activities take place and where policies, procedures, and strategies are defined for each of theprocesses, which govern the conduct of the engagement.

*In OUM Manage, one of the first activities that occur during the Project Startup phase involves the Project Manager and the client (Project Sponsor) jointly creating the Project Management Framework. This framework establishes the ground rules for the project and is the first step in communicating, establishing trust, and setting expectations.

The key focus for the remainder of the Project Startup Phase is to evolve the Project Management Framework into a detailed Project Management Plan based on the agreed upon foundation. In prior versions of OUM Manage, the equivalent work product was named the "Terms of Reference". Literally, this was the work product referenced to sort out problems when future misunderstandings occurred.

Incorrect: Not B Not F

Questions 11

Select three types of Envision engagements.

A. Establish an enterprise IT Governance process.

B. Install and configure an application.

C. Define a SOA enterprise engineering process.

D. Design and build a custom application.

E. Implement an Enterprise Repository.

F. Integrate an off-the-shelf application with another application.

Buy Now

Correct Answer: ACD

The Envision focus area provides a framework for development and maintenance of enterprise level IT strategy, architecture, and governance. The Envision guidance helps project team's transition from enterprise-level planning and strategy activities to the identification and initiation of specific projects.

Questions 12

Which three statements are true about the Validated Scope of the project?

A. It uses outputs of the Bid Transition process as a prerequisite.

B. It documents the boundaries of the project.

C. It documents only contractual deliverables.

D. It documents the contents of the Work Breakdown Structure.

E. It is a key input to the Project Management Plan.

Buy Now

Correct Answer: BDE

B: Scope Management - The goal of the Scope Management process is to identify clear boundaries of what is to be implemented and what key work products are to be produced.

D:A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into their successively higher level "parent" tasks, materials, etc. For each element of the work breakdown structure, a description of the taskto be performed is generated.This technique (sometimes calleda system breakdown structure) is used to define and organize the total scope of a project.

Questions 13

What is one of the first outputs of the Project Execution and Control Phase?

A. Staff retention plan

B. Team orientation and kickoff

C. Project sponsor orientation and kickoff

D. Go-live cutover

E. Contractsign-off

Buy Now

Correct Answer: D

Note: The purposeof the Project Execution and Control Phase is to provide adequate visibility into actual progress so thatmanagement can take effective actions when the project's performance deviates significantly from theproject plans. The Project Execution and Control Phase includes tracking and reviewing the projectsaccomplishments and results against documented WBS, project estimates, time schedule, resourcesplan, and cost budget, and adjusting these plans based on the actual accomplishment and results.

Exam Code: 1Z0-466
Exam Name: Project Lifecycle Management Essentials
Last Update: May 24, 2026
Questions: 98

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2026 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.