Which Oracle Unified Method phase includes Bid Transition?
A. Project Start Up
B. Project Closure
C. Project Executing and Control
D. Financial Management
What is true about planning a project in OUM Manage?
A. All tasks are executed to the same degree during the Project Execution and Control phase.
B. There is no distinction between executing and controlling the project and executing and controlling an iteration/phase.
C. The project plan that is established in the Project Startup phase details each task through the end of the project.
D. Manage tasks are not included in the project work plan.
Select the three applicable goals of the OUM Manage Focus Area.
A. Identify and communicate with project stakeholders.
B. Effectively transition from the sales (bid) process to Project Start Up
C. Manage to reduce overall project risk.
D. Define scope of work.
E. Decreases implementation time.
F. Create better project plans.
Earned value is a technique to report project status using which three variables?
A. EV ?Earned Value
B. PV ?Planned Value
C. AC ?Actual Cost
D. PC ?Planned Cost
E. EC ?Earned Cost
What does OUM Manage recommend for stakeholder involvement?
A. the project sponsor is the only stakeholder involved in Bid Transition
B. the steering committee is formed during Project Execution and Control
C. stakeholders be engaged early in the project
D. only internal stakeholders should identify risks and issues
E. work products are reviewed by all stakeholders identified in the contract
Which term means executing the systematic quality activities to determine if the quality processes are being followed and whether they are satisfying the project quality needs?
A. Quality Planning
B. Quality Control
C. Quality Assurance
D. Process Improvement
Select the three major activities in the Project Start Up phase.
A. Develop Staff Plan and Budget
B. Manage Project Quality
C. Validate Scope, Stakeholders, and OCM Strategy
D. Review Bid and Contract
E. Establish Estimate
F. Develop DetailProject Plan
Select three types of Envision engagements.
A. Establish an enterprise IT Governance process.
B. Install and configure an application.
C. Define a SOA enterprise engineering process.
D. Design and build a custom application.
E. Implement an Enterprise Repository.
F. Integrate an off-the-shelf application with another application.
Which three statements are true about the Validated Scope of the project?
A. It uses outputs of the Bid Transition process as a prerequisite.
B. It documents the boundaries of the project.
C. It documents only contractual deliverables.
D. It documents the contents of the Work Breakdown Structure.
E. It is a key input to the Project Management Plan.
What is one of the first outputs of the Project Execution and Control Phase?
A. Staff retention plan
B. Team orientation and kickoff
C. Project sponsor orientation and kickoff
D. Go-live cutover
E. Contractsign-off