The ProjectManager selects the "Update units when costschange on resource assignments"optionon Calculations tab in Project Details. The Budgeted Cost is $2,000 and the Budgeted Units is 80 for the resource on an activity. If the User assigns the activity an Actual Cost of $1,000, what is the Actual Units for the resource?
A. 70
B. 40
C. 60
D. 80
You can create a Calculated User Defined Field for which Subject Area?
A. Activity
B. Resource
C. Project
D. Security
When is"Store Period Performance" usually performed?
A. aftereachpay period
B. after the schedule isupdated
C. after Job Servicesvalidation
D. after working hours to enhanceperformance
Select the true statement regarding Project level Security Profiles.
A. Project Security Profiles define the weight of Project Codes.
B. To access projects, a user must be defined in the Resource Hierarchy.
C. Project Security Profiles override Global Security Profiles.
D. To access projects, a user must be assigned a Project Security Profile.
The Open Requests for Resources portlet lists unstaffed assignments Involving Roles on the selectedRole Team.
Identify the two ways that the portlet display can be customized.
A. Role by Project
B. Role by Resource
C. Project by Role
D. Resource by Project
E. Resource by Role
What is the highest level of a Work Breakdown Structure (WBS)
A. Enterprise
B. Portfolio
C. Program
D. Project
Select the true statement regarding currencies.
A. Only one base currency is supported per database.
B. Currencies are updated dally as pet exchange rates.
C. Only 10 currencies are supported in Primavera.
D. Only two currencies are supported in Primavera.
Select the statement that best describes a global portfolio.
A. It is available to single users.
B. It is assigned by a filter.
C. It must be manually refreshed.
D. It is available to all users.
E. Access is governed by security.
You are a Project Manager that used Primavera P6 EPPM Web interface.You are trying to determine ifsome Project level User Defined Fields might be appropriate for one of your projects.YoulaunchPrimavera P6 EPPM Clientto view enterprise data. You areunable to launch theapplication.
What is the probable issue that must be addressed with your System Administrator?
A. You do not have appropriate security privileges.
B. You do not have appropriate license.
C. You are not a Responsible Manager.
D. You need additional memory added to your machine.
In your project, cost and work effort is not subject to change.
Which duration type should beused?
A. Fixed Units
B. Fixed Duration and Units/Time
C. Fixed Units/Time
D. Fixed Duration and Units