Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > AACE International > AACE International Certifications > AACE-PSP > AACE-PSP Online Practice Questions and Answers

AACE-PSP Online Practice Questions and Answers

Questions 4

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

A. Industry publications.

B. Critical path schedules prepared by you for similar completed projects.

C. The Petrochemical Industry New Plant Task Duration Handbook.

D. The cost estimate for the plant prepared by your firm's estimating department.

Buy Now

Correct Answer: B

Questions 5

These are the activities on the critical path: A. A, D, and I.

B. A, C, E, and H.

C. A, B, G, and H.

D. A, B, F, and J

Buy Now

Correct Answer: C

Questions 6

When resource leveling craft labor for a critical path schedule, the scheduler

A. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D. Need only consider the non-union crafts persons.

Buy Now

Correct Answer: B

Questions 7

Project delays are best analyzed

A. After either the contractor or the owner acknowledges ^responsibility for the delay.

B. Contemporaneously with the delay.

C. By an expert after the project is finished when complete records are available and the impact is known.

D. Late in the project.

Buy Now

Correct Answer: C

Questions 8

Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

A. 12-27-03 and 24 days of float

B. 12-18-03 and 4 days of float

C. 12-17-03 and 4 days of float

D. 12-18-03 and 25 days of float

Buy Now

Correct Answer: C

Questions 9

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

A. 15 days.

B. 10 days.

C. 0 days.

D. 5 days.

Buy Now

Correct Answer: C

Questions 10

What owner action could have mitigated the late completion of the project?

A. Hire a more senior project manager.

B. Self-perform more of the work.

C. Use a procurement agent to monitor and expedite equipment deliveries.

D. Prepare better structural steel drawings.

Buy Now

Correct Answer: C

Questions 11

At a minimum, periodic reporting must be done at what interval?

A. Monthly.

B. As requested by the project manager.

C. As requested by the owner.

D. As specified in the contract documents.

Buy Now

Correct Answer: D

Questions 12

Project schedules help control all of the following EXCEPT for_____________________.

A. Quality

B. Cost

C. Resources

D. Time

Buy Now

Correct Answer: A

Questions 13

By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

A. Acceleration.

B. Production output.

C. Productivity loss.

D. Productivity efficiency.

Buy Now

Correct Answer: C

Exam Code: AACE-PSP
Exam Name: Planning & Scheduling Professional (PSP)
Last Update: Jul 04, 2026
Questions: 120

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2026 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.