In a free format Timebox, when should reviews take place?
A. During the Kick-Off phase
B. Throughout the body of the Timebox.
C. During the Close.Out phase
D. After the Timebox has been completed
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?
A. Foundation Summary
B. Delivery Plan
C. Terms of Reference
D. Management Approach Definition
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.
A. Governor
B. Champion
C. Visionary
D. director
Which practice provides an interactive environment in which all key players can contribute to the outcome?
A. Modelling
B. Facilitied Wordshop
C. Iterative Development
D. Timeboxing
Which plain defined by DSDM, has a planning horizon that includes the end of a project?
A. Timebox
B. Detailed
C. Delivery
D. High-Level
What is the purpose of the Foundations Summary?
A. To document how stakeholders will be engaged and standards that will be applied.
B. To define the tools, techniques, customer, practices and standards that will be applied
C. To provide enough information to decide whether the project is likely to deliver return on investment
D. To define the scope of the requirements that the project needs to address
During what phase should the strategy for Iterative Development be considered?
A. Pre-Project
B. Feasibility
C. Foundations
D. Evolutionary Development
Which responsibility relates to the role of the Business Ambassador?
A. Provide the team with strategic direction.
B. Responsible for the Business Case and project budget.
C. Resolve business issues and make financial decisions
D. Provide day-to-day detail of the requirements during timeboxes
How is Quality ensured during Evolutionary Development?
A. By managing objectives in a fixed time period
B. By continuous verification
C. By understanding and managing priorities
D. By facilitating session to enable a group to work to achieve an agreed goal
In what phase is it first established whether further investigation of the project is justified?
A. Pre-Project
B. Feasibility
C. Foundations
D. Evolutionary Development