Which of the following is a key characteristic of the Agile project approach?

A. Frequent quality gates

B. Frequent and detailed project scheduling

C. Formal and detailed documentation

D. Iterative build with frequent inspections

Buy Now

Correct Answer: D

D is correct because Iterative build with frequent inspections is a key characteristic of the Agile project approach. The Agile project approach follows an iterative and incremental development process, where the solution is built and delivered in small increments called sprints. Each sprint consists of planning, designing, building, testing, and reviewing activities, where the team inspects the solution and adapts to changing requirements and feedback

Questions 5

What is preferred when a customer wants to keep most of their original processes and migrate to SAP S/4HANA Cloud, private edition?

A. Mix and Match

B. System Conversion

C. Shell Conversion

D. Selective Data Transition

Buy Now

Correct Answer: C

Shell Conversion is preferred when a customer wants to keep most of their original processes and migrate to SAP S/4HANA Cloud, private edition. It involves creating a shell system that contains the configuration and master data of the

source system, and then migrating the transactional data to the target system.

Verified References:

SAP Activate Project Management Certification Guide, page 128

Questions 6

Which of the following are capabilities of the test automation tool for SAP S/4HANA Cloud, public edition?Note: There are 2 correct answers to this question.

A. Raises test defects automatically

B. Supports recording of transaction-based processes

C. Captures test results with screenshots

D. Supports the creation of custom test automates

Buy Now

Correct Answer: BD

B is correct because the test automation tool for SAP S/4HANA Cloud, public edition supports recording of transaction-based processes. This means that the tool can capture the user actions and inputs during a transaction and generate a

test script that can be replayed later.

D is correct because the test automation tool for SAP S/4HANA Cloud, public edition supports the creation of custom test automates. This means that the tool allows the user to modify the existing test scripts or create new ones from scratch,

using a graphical user interface or a scripting language.

Verified References:

Test Automation Tool for SAP S/4HANA Cloud, Public Edition ?A Game Changer in the 3-System Landscape

SAP S/4HANA Cloud Test Automation Tool ?Our Approach to Test Automation

Questions 7

When performing an SAP Readiness Check in system conversion, what areas are covered within the result?Note: There are 3 correct answers to this question

A. Recommended SAP Fiori apps

B. SAP and third party interfaces

C. Sizing for SAP S/4HANA

D. Active business functions

E. Simplification database

Buy Now

Correct Answer: ACE

A is correct because SAP Readiness Check in system conversion covers the area of recommended SAP Fiori apps, which are apps that are suggested by SAP based on the customer's current usage of SAP GUI transactions.

C is correct because SAP Readiness Check in system conversion covers the area of sizing for SAP S/4HANA, which is an estimation of the hardware and software resources required to run SAP S/4HANA based on the customer's current

system data.

E is correct because SAP Readiness Check in system conversion covers the area of simplification database, which is a collection of simplification items that describe the changes and adaptations required for SAP S/4HANA compared to the

previous SAP ERP releases.

Verified References:SAP Readiness Check 2.0 for SAP S/4HANA

Questions 8

Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package?Note: There are 2 correct answers to this question.

A. Configuration Guides

B. Scope Items

C. Building Blocks

D. Business Process Scenarios

Buy Now

Correct Answer: BC

B is correct because Scope Items are one of the levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package. A Scope Item is a unit of business functionality that covers one or more business processes. A Scope Item

has a description, a list of configuration steps, and a set of test cases.

C is correct because Building Blocks are one of the levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package. A Building Block is a reusable component that contains configuration data, master data, or transactional

data for a specific business area. A Building Block can be assigned to one or more Scope Items.

Verified References:[SAP Best Practices Explorer]

Questions 9

Which of the following tools can support you in managing requirements and software development for implementation projects? Note: There are 2 correct answers to this question

A. SAP Focused Run

B. Focused Build for SAP Solution Manager

C. Focused Insights for SAP Solution Manager

D. SAP Cloud ALM

Buy Now

Correct Answer: BD

B is correct because Focused Build for SAP Solution Manager is a tool that supports the management of requirements and software development for implementation projects. It provides features such as requirements-to-deploy process,

collaboration platform, quality gate management, and test management.

D is correct because SAP Cloud ALM is a tool that supports the management of requirements and software development for implementation projects. It provides features such as project task management, solution documentation, change

request management, and test management.

Verified References:Focused Build for SAP Solution Manager SAP Cloud ALM

Questions 10

Which of the following are SAP Activate workstreams?Note: There are 2 correct answers to this question.

A. Change Management

B. Project Management

C. Extensibility

D. Data Migration

Buy Now

Correct Answer: BD

B is correct because Project Management is one of the SAP Activate workstreams. The Project Management workstream covers all the activities related to planning, executing, monitoring, controlling, and closing the project. It includes tasks such as defining project scope, schedule, budget, resources, risks, issues, quality, communication, and stakeholder management. D is correct because Data Migration is one of the SAP Activate workstreams. The Data Migration workstream covers all the activities related to preparing, extracting, transforming, validating, and loading data from legacy systems to SAP systems. It includes tasks such as defining data migration strategy, scope, approach, tools, roles, responsibilities, quality criteria, and testing scenarios. Verified References: SAP Activate Methodology Workstreams Names update SAP Activate Testing Workstream

Questions 11

When applying a cloud mindset in a greenfield Implementation, which of the following should you consider?Note: There are 2 correct answers to this question.

A. Use supported extensibility technologies

B. Use quality gates

C. Apply SAP quality principles

D. Ensure transparency on deviations

Buy Now

Correct Answer: AD

A is correct because a cloud mindset means embracing the cloud capabilities and avoiding unnecessary customizations that could impact the performance, scalability, and maintainability of the solution. Therefore, using supported extensibility technologies is important to ensure compatibility and compliance with the cloud environment. D is correct because a cloud mindset also means ensuring transparency on deviations from the standard SAP functionality and documenting the rationale and impact of any customizations or extensions that are required to meet the customer needs. Verified References: SAP Activate Project Management Certification Guide, page 129 SAP Activate Methodology for SAP S/4HANA Cloud, page 16

Questions 12

What information does the project team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question.

A. Available project resources

B. Definition of Ready

C. Definition of Done

D. Benchmark user story

Buy Now

Correct Answer: BC

Definition of Done is the information that the project team needs before they can correctly estimate the relative size of backlog user stories. Definition of Done is a set of criteria that determines when a user story is considered complete and ready for acceptance by the product owner. It helps the team to align their expectations and assumptions on each user story, and provide consistent and reliable estimates.

Questions 13

In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?

A. Deploy

B. Prepare

C. Explore

D. Realize

Buy Now

Correct Answer: C

C is correct because in the Explore phase, you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps. This is done through a fit-to-standard workshop, where you compare the customer's business requirements with the standard SAP functionality, and document any gaps or deviations as user stories. Verified References:SAP Activate Project Management Certification Guide, page 122

Exam Code: C_ACT_2403
Exam Name: SAP Certified Associate - Project Manager - SAP Activate
Last Update: May 24, 2026
Questions: 82

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2026 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.