All the currency-dependent data in the Project System is managed in three different currencies in parallel.
These are;
There are 3 correct answers to this question.
Response:
A. Business Area Currency
B. Controlling area currency
C. Object Currency
D. Transaction currency
Response:
A. Copying a Material BOM
B. Copying a sales order BOM
C. Copying other WBS BOM
D. BOM copy function
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity? Please choose the correct answer.
A. Workforce planning board
B. Project planning board
C. Work center planning board
D. Capacity planning board
In progress tracking what are the different ways of assigning the dates of events that are assigned to network components while evaluation? There are 3 correct answers to this question.
A. Using BADIs
B. Generation and assignment of a new event
C. Direct assignment of a new event
D. Direct assignment of a standard event
Which type of confirmation allows you to enter the actual start and finish date, forecast finish date and forecast work in a tabular format? Please choose the correct answer.
A. Group confirmation
B. Single confirmation
C. Individual confirmation
D. Collective confirmation
With reference to material requirements in Project System (PS-MAT), which of the following statements
are true?
Please choose the correct answer.
A. Component scrap is considered during BOM explosion.
B. Project System supports consignment stock.
C. 9999 components may be created per network.
Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in
addition to enable milestone billing? There are 2 correct answers to this question.
Response:
A. Activate milestone functions.
B. Activate indicator sales document date for milestones.
C. Create a billing plan assigned to a sales order item.
D. Set up percentage of completion for milestones.
E. Create a billing plan assigned to a WBS element.
In internal processing which views allow you to easily and quickly assign persons to activities and use
various data (availability of the person from Human Resources, the total work planned for that person, or
the activity date)? There are 2 correct answers to this question.
Response:
A. Project view
B. Resource view
C. Work center view
D. Assignment view
In which type of project stock costs from external procurement are posted directly to the stock-keeping WBS element when the goods or invoice are received? Please choose the correct answer. Response:
A. No project stock
B. Valuated project stock
C. Non-valuated project stock
D. Sales order project stock
When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following? There are 2 correct answers to this question. Response:
A. Tasks
B. WBS
C. Activities
D. Operations