What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question
A. Settlement
B. Milestone trend analysis
C. Confirmations
D. Progress analysis
E. Results analysis
How can you record external service activities with service master data? Note: There are 2 correct answers to this question
A. Confirm the network activity for external service
B. Confirm the activities in the Cross-Application Time Sheet (CATS)
C. Post a goods receipt in the goods movement application (MIGO)
D. Create a service entry sheet
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
A. An activated Scheduling indicator in the control key of the internal processing activity
B. Whether the work for the internal activity is greater than its duration
C. The unit (for example, hour, day) of the field Normal Duration field of the activity
D. The relationships between activity elements
E. The factory calendar in the work center used for the internal processing activity
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question
A. Duration
B. Activity type
C. Work
D. Profit center
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.
A. Reservations
B. Sales order items
C. Purchase order items
D. Internal orders
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?
A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
B. Set up the requirement date manually as February 5.
C. Set up the requirement date aligned with the activity start date and an offset of 5 days
D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
A. Actual dates of the network activity
B. Basic dates of the WBS
C. Forecast dates of the WBS
D. Basic dates of the network activity
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
A. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)
B. The purchase order is updated automatically to match the new quantity while saving the project.
C. A workflow can be triggered to inform the purchasing group.
D. The system automatically creates a new purchase requisition with the difference to the original quantity
You are working with networks and WBS elements. Which of the following statements applies
A. You can reassign an activity from one network to another
B. You can assign the network header to multiple WBS elements
C. You have to maintain a network profile in the project profile
D. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?
A. The manual hierarchical revenue planning will be displayed only if expert mode is activated
B. The manual hierarchical revenue planning has no reference to cost elements
C. Cost element reports can display costs but not revenues
D. Cost element reports display integrated planning only