Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > SAP > SAP Certifications > C_TS412_2021 > C_TS412_2021 Online Practice Questions and Answers

C_TS412_2021 Online Practice Questions and Answers

Questions 4

What functions are available for period end closing in SAP Project System? Note: There are 3 correct answers to this question

A. Settlement

B. Milestone trend analysis

C. Confirmations

D. Progress analysis

E. Results analysis

Buy Now

Correct Answer: ADE

Settlement, progress analysis, and results analysis are some of the functions available for period end closing in SAP Project System. Settlement is used to allocate the costs andrevenues in projects or the results analysis data to one or more receivers, such as cost centers, profitability segments, or assets. Progress analysis is used to determine and compare the planned and actual project progress values, based on the overall planned costs and the work done. Results analysis is used to perform a periodic valuation of the project, based on the costs and revenues expected or incurred in the project. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/enUS/6a7a9f0a6e421014e10000000a174cb4.html

Questions 5

How can you record external service activities with service master data? Note: There are 2 correct answers to this question

A. Confirm the network activity for external service

B. Confirm the activities in the Cross-Application Time Sheet (CATS)

C. Post a goods receipt in the goods movement application (MIGO)

D. Create a service entry sheet

Buy Now

Correct Answer: BD

To record external service activities with service master data, you can confirm the activities in the Cross-Application Time Sheet (CATS) or create a service entry sheet. Service master data is a set of data that defines the scope and details of a service to be performed by an external vendor for a project activity. Confirming the activities in CATS is an action that records the time spent on performing external services and posts actual costs to the project. Creating a service entry sheet is an action that records the delivery of external services and posts actual costs to the project. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 6

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

A. An activated Scheduling indicator in the control key of the internal processing activity

B. Whether the work for the internal activity is greater than its duration

C. The unit (for example, hour, day) of the field Normal Duration field of the activity

D. The relationships between activity elements

E. The factory calendar in the work center used for the internal processing activity

Buy Now

Correct Answer: ADE

The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Reference:https://help.sap.com/ doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 7

You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

A. Duration

B. Activity type

C. Work

D. Profit center

Buy Now

Correct Answer: AB

To determine the planned costs for an internally processed activity, you need the duration and activity type data. The duration is the time required to complete the activity. The activity type is a classification of activities according to their functions or characteristics. The system calculates the planned costs for an internally processed activity based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 8

Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.

A. Reservations

B. Sales order items

C. Purchase order items

D. Internal orders

Buy Now

Correct Answer: AC

Project-Oriented Procurement (ProMan) is a tool that allows you to display and process procurement documents that are relevant for projects. You can use ProMan to display reservations and purchase order items that are assigned to WBS elements or network activities. You can also use ProMan to create purchase requisitions, purchase orders, goods movements, and invoices for project-related materials and services. Reference:https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e1000 0000a174cb4/frameset.htm

Questions 9

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B. Set up the requirement date manually as February 5.

C. Set up the requirement date aligned with the activity start date and an offset of 5 days

D. Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Buy Now

Correct Answer: D

To set up the requirement date for the component so that it will be in stock 5 days in advance of the assembly activity, you should set up the requirement date aligned with the activity start date and a negative offset of 5 days. The requirement date is the date on which a material component is required for an activity. The offset is a value that shifts the requirement date forward or backward from the activity start or finish date. A negative offset means that the requirement date is earlier than the activity date. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 10

You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

A. Actual dates of the network activity

B. Basic dates of the WBS

C. Forecast dates of the WBS

D. Basic dates of the network activity

Buy Now

Correct Answer: D

To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. The requirement date for a material component is derived from the basic start date of the activity to which it is assigned. Reference:https://help.sap.com/ doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 11

In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

A. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)

B. The purchase order is updated automatically to match the new quantity while saving the project.

C. A workflow can be triggered to inform the purchasing group.

D. The system automatically creates a new purchase requisition with the difference to the original quantity

Buy Now

Correct Answer: C

When you increase the quantity of the external activity after creating a purchase requisition and a purchase order, a workflow can be triggered to inform the purchasing group. A workflow is a process that automates and controls business tasks according to predefined rules and conditions. A workflow can be triggered when certain events occur in a project, such as changes in quantities, dates, or statuses of project objects. A workflow can perform various actions, such as sending notifications, creating documents, or calling transactions. In this scenario, a workflow can be triggered when you increase the quantityof the external

Questions 12

You are working with networks and WBS elements. Which of the following statements applies

A. You can reassign an activity from one network to another

B. You can assign the network header to multiple WBS elements

C. You have to maintain a network profile in the project profile

D. You have to activate the operative indicator Account Assignment Element for WBS element with activities.

Buy Now

Correct Answer: C

One of the statements that applies to working with networks and WBS elements is that you have to maintain a network profile in the project profile. A network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. A project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. You have to assign a network profile to a project profile in order to create networks within a project. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 13

You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?

A. The manual hierarchical revenue planning will be displayed only if expert mode is activated

B. The manual hierarchical revenue planning has no reference to cost elements

C. Cost element reports can display costs but not revenues

D. Cost element reports display integrated planning only

Buy Now

Correct Answer: B

The reason why the cost element report for planned revenues does not show any revenues at all is that the manual hierarchical revenue planning has no reference to cost elements. Manual hierarchical revenue planning is a type of revenue planning that allows you to plan revenues for WBS elements manually without using sales documents. Manual hierarchical revenue planning does not use cost elements as a basis for planning, but uses revenue elements instead. Revenue elements are a set of data that define the characteristics and properties of a revenue type. Cost element reports can only display data that is based on cost elements, not revenue elements. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Exam Code: C_TS412_2021
Exam Name: SAP Certified Associate - SAP S/4HANA Project Systems
Last Update: May 27, 2026
Questions: 110

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2026 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.