Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

A. Network profile

B. Project profile

C. Parameters for the network type

D. Network type

Buy Now

Correct Answer: D

Network type is an object that defines whether a network is "header-account-assigned" or "activity-account-assigned". Header-account-assigned networks have only one account assignment at the network header level, which applies to all activities in the network. Activity-account-assigned networks have different account assignments at each activity level, which allows more flexibility and granularity in cost allocation and reporting. Reference:https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html

Questions 5

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"

B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"

C. You can always maintain the actual start and finish date of a WBS element

D. You can only maintain the actual start of a WBS element if the finish date is not maintained

Buy Now

Correct Answer: BC

If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially released", which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element. Reference:https://help.sap.com/ doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 6

For which objects can billing plans be created? Note: There are 2 correct answers to this question

A. WBS elements

B. Project definition

C. Sales order items

D. Milestones

Buy Now

Correct Answer: AC

Billing plans can be created for WBS elements and sales order items. Billing plans areused to define billing dates and billing amounts for periodic or milestone billing. WBS elements can be assigned to billing plans if they are assigned to a sales document item or if they have a billing element indicator set. Sales order items can be assigned to billing plans if they have a relevant item category and billing relevance. Reference:https://help.sap.com/ doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 7

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

A. An activated Scheduling indicator in the control key of the internal processing activity

B. Whether the work for the internal activity is greater than its duration

C. The unit (for example, hour, day) of the field Normal Duration field of the activity

D. The relationships between activity elements

E. The factory calendar in the work center used for the internal processing activity

Buy Now

Correct Answer: ADE

The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Reference:https://help.sap.com/ doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Questions 8

Project Structures

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.

What are the prerequisites? Note: There are 3 correct answers to this question

A. A bill of material with sales views

B. A material master with sales views

C. Assignment between material and standard network

D. Standard network with activities

E. A production order

Buy Now

Correct Answer: BCD

According to SAP Press, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network."

Questions 9

You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?

Note : there are 2 correct answers for this question.

A. Use an offset of two days for the relationship of both activities.

B. Use an offset of two days for milestone date.

C. Use an offset of two days for the requirement date of the material component

D. Calculate the start date of the activity and set the constraint "Must start on" accordingly.

Buy Now

Correct Answer: AD

"You can use an offset to specify a time interval between two activities. For example, you can specify that an activity should start two days after its predecessor activity has finished." According to SAP Help Portal2, "You can use constraints to specify fixed dates for activities. For example, you can use the constraint `Must start on' to fix the start date of an activity."

Questions 10

Project Structure

Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.

What standard report do you recommend?

A. Structure overviews for budget.

B. Cost element report on budget updates.

C. Line item report for budget

D. Hierarchical report on budget updates.

Buy Now

Correct Answer: D

A hierarchical report on budget updates is a standard report that you can use to get an overview of the budget changes for your projects. This report displays the original budget, current budget, budget updates, and budget transfers for each WBS element in a hierarchical structure. You can also drill down to see the details of each budget update document. You can access this report by choosing Information System Reports Financials Costs Budget Hierarchical Report on Budget Updates . Reference:https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.h tml?andversion=1909.002

Questions 11

You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?

Note : there are 2 correct answers for this question.

A. The procurement type in the material master is set to in-house Production.

B. The item category of the materials is set tstock item.

C. The material have no material number.

D. The item category of the materials is set tnon-stock item.

Buy Now

Correct Answer: AC

To create purchase requisitions for the materials used in your project, you must ensure that the materials have a procurement type that allows external procurement and a material number that identifies them uniquely. Some of the possible

reasons why no purchase requisitions have been created after releasing the project are:

The procurement type in the material master is set to in-house production (E). This means that the material is produced internally and not procured externally from a vendor.

The material has no material number (N). This means that the material is a non-stock item that is not managed in inventory and has no master record. Non-stock items require manual creation of purchase requisitions.

Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?andversion=1909.002

Questions 12

Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

A. Project-relevant purchase orders

B. Capacity requirements

C. Maintenance orders assigned to an activity

D. Production orders assigned to WBS elements

Buy Now

Correct Answer: BC

The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference:https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-USandstate=PRODUCTIONandversion=2020.002

Questions 13

When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

A. Service specification

B. Overall limit (maximum value of all unplanned services)

C. Service purchase order number

D. Material master within service specification

E. Vendor

Buy Now

Correct Answer: ABE

When you create a service activity in your network, you can enter a service specification, an overall limit, and a vendor. The service specification defines the scope and details of the service to be performed. The overall limit sets a maximum value for all unplanned services that can be entered during service entry. The vendor specifies the external service provider who will perform the service. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html

Exam Code: C_TS412_2021
Exam Name: SAP Certified Associate - SAP S/4HANA Project Systems
Last Update: Jun 09, 2025
Questions: 110

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2025 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.