Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > SAP > SAP Certifications > C_TSCM42_67 > C_TSCM42_67 Online Practice Questions and Answers

C_TSCM42_67 Online Practice Questions and Answers

Questions 4

You select the master data for production orders via production versions.

Which information is contained in a production version?

A. The explosion dates for the routing and BOM

B. The routing and BOM alternatives to be used

C. The default order type to be used

D. The control parameters for selecting routings and BOM

Buy Now

Correct Answer: B

Questions 5

What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)

A. The order is no longer relevant for material requirements planning.

B. Capacity requirements are set to null.

C. Confirmations are no longer possible.

D. Reservations are no longer relevant for material requirements planning.

E. The order and its operations receive the system status Locked (LKD).

Buy Now

Correct Answer: ABD

Questions 6

What are characteristics of repetitive manufacturing? (Choose three)

A. Production without using production orders and without status management

B. Shop fabrication

C. Automatic line loading based on capacity limits across all production lines

D. Continuous material consumption, production flow and output

E. Period-based planning of the quantities to be produced

Buy Now

Correct Answer: ADE

Questions 7

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon.

What procedure would you recommend to the project team for setting the planning horizon on the system side?

A. The planning horizon is set in the MRP groups in Customizing and variant entries are assigned via the plant parameter settings.

B. The planning horizon is set in Customizing using the plant parameter setting and variant entries are assigned via the MRP groups for the materials in question.

C. The planning horizon is set in the MRP groups in Customizing and the variant values are stored in the material masters for the materials in question.

D. The planning horizon is set in the plant parameters in Customizing and variant entries are stored in the material masters for the materials in question.

Buy Now

Correct Answer: B

Questions 8

Which Customizing element controls the determination of planned costs in production orders?

A. Accounting type

B. Costing variant

C. Calculation procedure

D. Settlement profile

Buy Now

Correct Answer: B

Questions 9

When modeling in-house production using SAP ECC, on which business levels can you create a bill of material (BOM)? (Choose two)

A. At the company code level

B. At the plant level

C. At the business area level

D. At the client level

Buy Now

Correct Answer: BD

Questions 10

Which of the following master data is necessary for the creation of material reservations for production orders?

A. Material master records

B. Production/resource tools

C. Routings

D. Production versions

Buy Now

Correct Answer: A

Questions 11

Which of the following items of master data are needed for repetitive manufacturing? (Choose three)

A. Production supply area

B. Repetitive manufacturing profile

C. Production version

D. Master record for serial numbers

E. Product cost collector

Buy Now

Correct Answer: BCE

Questions 12

Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?

A. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.

B. Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.

C. Assign an appropriate availability checking rule to the material master for the product.

D. Activate the availability check and assign an overall profile in the production scheduling profile.

Buy Now

Correct Answer: B

Questions 13

Which of the following requirements for a manufacturing plant can be supported by using process manufacturing? (Choose three.)

A. Master recipe-based manufacturing.

B. Material requirements planning for production resources.

C. Manufacturing without orders.

D. Variable calculation of material quantities (product output, material usage).

E. Manufacturing in charge quantities.

Buy Now

Correct Answer: ADE

Exam Code: C_TSCM42_67
Exam Name: SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7
Last Update: May 27, 2026
Questions: 106

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2026 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.