Questions 4

On the demand form, what does the Discount Rate impact?

A. ROI.

B. Net Present Value (NPV).

C. Financial Benefit.

D. Internal Rate of Return %.

Buy Now

Correct Answer: B

According to the ServiceNow documentation1, the discount rate on the demand form impacts the net present value (NPV) of the demand. The NPV is the difference between the present value of the benefits and the present value of the costs of the demand. The discount rate is the rate used to discount future cash flows to their present value. A higher discount rate means that future cash flows are worth less in the present, and vice versa. The other options are incorrect because:

A. ROI: The ROI (return on investment) is the ratio of the net value to the estimated cost of the demand. The discount rate does not affect the ROI, as both the net value and the estimated cost are based on the present value of the cash flows.

C. Financial Benefit: The financial benefit is the sum of the present value of the benefits of the demand. The discount rate does not affect the financial benefit directly, but only indirectly through the NPV calculation.

D. Internal Rate of Return %: The internal rate of return % (IRR) is the discount rate that makes the NPV of the demand equal to zero. The discount rate does not affect the IRR, but rather the IRR is derived from the NPV equation.

https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/reference/r_DemandTable.html https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_DemandRate.html

https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_FinancialBenefit.html https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/concept/c_InternalRateOfReturn.html

Questions 5

The Business Unit field on a Project or Demand form displays values from a specific table. What type of field is this?

A. Journal.

B. Reference.

C. Conditions.

D. List.

Buy Now

Correct Answer: B

According to the ServiceNow documentation1, the Business Unit field on a Project or Demand form is a reference field that displays values from the cmn_department table. A reference field stores a link to a record on another table, rather than storing the data directly in the field.

https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_ProjectTable.html https://docs.servicenow.com/bundle/vancouver-platform-administration/page/administer/form-administration/concept/c_ReferenceFields.html

Questions 6

If a lens has four entities, which entity within the lens structure would not have a parent reference?

A. Top-level entity

B. Second-level entity

C. Third-level entity

D. Bottom entity

Buy Now

Correct Answer: A

According to the ServiceNow documentation1, a lens is a hierarchical structure that consists of entities and relationships. An entity is a data object that represents a business concept, such as a project, a demand, or a resource. A relationship is a link between two entities that defines how they are connected. A lens can have up to four levels of entities, each with a parent reference to the entity above it, except for the top-level entity, which has no parent reference. The top-level entity is the root of the lens and defines its scope and type. For example, a project lens has a project as the top-level entity, and a demand lens has a demand as the top-level entity. https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/it-business-management/concept/c_Lens.html

Questions 7

Depending on the execution type selected for a particular project, one of these dashboards will also be available:

A. Project Summary - Waterfall Dashboard

B. Timecard Dashboard

C. User Manager Dashboard

D. PMO Dashboard

Buy Now

Correct Answer: A

According to the Project Summary - Waterfall Dashboard document, depending on the execution type selected for a particular project, the Project Summary - Waterfall Dashboard will also be available. This dashboard provides a comprehensive view of the project status, progress, and performance using various widgets. The other options are not correct, as they are not dashboards that are dependent on the execution type of the project. The Timecard Dashboard is a dashboard that displays the time worked by users on various tasks. The User Manager Dashboard is a dashboard that displays the user management activities and statistics. The PMO Dashboard is a dashboard that displays the portfolio and project performance and health.

Questions 8

If the 'Move project for WIP projects' property is enabled, project tasks associated with the project are also moved, except for tasks in which of the following states?

Choose 2 answers

A. Pending

B. Work in Progress

C. Closed

D. Open

Buy Now

Correct Answer: BC

According to the Planning Console document, if the `Move project for WIP projects' property is enabled, project tasks associated with the project are also moved, except for tasks in the Work in Progress or Closed states. The other options are not correct, as tasks in the Pending or Open states are moved along with the project.

Questions 9

Which demand category would a demand manager select, if they need to create an enhancement?

A. Defect

B. Change

C. Operational

D. Strategic

Buy Now

Correct Answer: C

Questions 10

What does the project status report allow project managers to do?

Choose 2 answers

A. View the project Gantt chart

B. View the WBS

C. Show historical trend of project KPI's

D. Print as a PDF attachment

Buy Now

Correct Answer: CD

The project status report allows project managers to do the following:

Show historical trend of project KPI's: The project status report displays the key performance indicators (KPIs) of the project, such as schedule variance, cost variance, and earned value. It also shows the historical trend of these KPIs over time, which helps project managers monitor the progress and performance of the project. You can find more information about the project status report KPIs in the Product Documentation for ServiceNow.

Print as a PDF attachment: The project status report can be printed as a PDF attachment and sent to the stakeholders or sponsors of the project. This helps project managers communicate the status and health of the project in a clear and concise format. You can find more information about the project status report PDF attachment in the Product Documentation for ServiceNow.

Questions 11

What is the formula for Committed Utilization?

A. Assigned Hours/Capacity

B. (Allocated Hours + Confirmed Hours)/Capacity

C. Confirmed Hours/Capacity

D. Allocated Hours/Capacity

Buy Now

Correct Answer: C

Questions 12

Where do you define 'Roles' requested via resource plans?

A. No need to define it differently, they are same as system roles.

B. Roles under system security.

C. Under skill management modules.

D. Resource roles under resource management.

Buy Now

Correct Answer: D

According to the Assigning Resource Roles document, you define `Roles' requested via resource plans under resource roles in the Resource Management application. Resource roles are the roles that users can request or allocate for resource plans. The other options are not correct, as they are not the places where you define `Roles' requested via resource plans. The system roles are the roles that grant access to various applications and modules in the system. The roles under system security are the roles that control the security settings and permissions for the system. The skill management modules are the modules that manage the skills and skill levels of users and groups.

Questions 13

What is the default table that stores the idea categories that a user can select from when submitting an idea?

A. dmn_demand

B. im_category

C. im_module

D. im_idea_core

Buy Now

Correct Answer: B

According to the Category Configuration document, the default table that stores the idea categories that a user can select from when submitting an idea is im_category. This table contains the predefined categories for ideas, such as Business Process, Customer Service, or IT Service. The other options are not correct, as they are not the tables that store the idea categories. The dmn_demand table stores the demand records that are created from the approved ideas. The im_module table stores the idea modules that are used to group ideas by different criteria. The im_idea_core table stores the core fields of the idea records.

Exam Code: CIS-SPM
Exam Name: Certified Implementation Specialist - Strategic Portfolio Management
Last Update: Jun 10, 2025
Questions: 60

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2025 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.