How many tasks does the product-based planning technique describe?
A. One
B. Two
C. Three
D. Four
Which characteristic distinguishes a project from regular business operations?
A. Produces benefits
B. Introduces business change
C. Manages stakeholders
D. Incurs cost
Which is a benefit of using PRINCE2?
A. Provides a defined structure of accountability, delegation, authority and communication
B. Includes techniques for critical path analysis and earned value analysis
C. Enables a Project Manager to be accountable for the success of a project
D. Prevents any changes once the scope of a project has been agreed
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enableit to finance new requirements.
A. change budget
B. cost tolerance
C. risk budget
D. scope tolerance
What product should be used to confirm the version number of ail products in a particular stage?
A. Issue Register
B. Product Status Account
C. Product Description
D. Configuration Item Record
Which is a purpose of an Exception Plan?
A. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
C. Identify the actions required to recover from the effect of a tolerance deviation
D. Define the changes which are within the scope of the change budget
Which is created during the Starting up a Project process?
A. Project mandate
B. Project management team role descriptions
C. Communication Management Strategy
D. Quality Register
When should the Project Board refer to corporate or programme management for a decision?
A. The stage requires resources
B. It is forecast that project level tolerance will be exceeded
C. The Senior Supplier or Senior User needs to be changed
D. Any request for change needs to be approved
Which is NOT included in the PRINCE2 definition of a project?
A. A project is a temporary organization
B. A project's purpose is to deliver one or more business products
C. A project is part ofbusiness as usual