Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > CompTIA > CompTIA Certifications > JK0-017 > JK0-017 Online Practice Questions and Answers

JK0-017 Online Practice Questions and Answers

Questions 4

Which of the following documents is used when soliciting vendors?

A. Request for Proposal (RFP)

B. Work Breakdown Structure (WBS)

C. Statement of Work (SOW)

D. Responsibility Assignment Matrix (RAM)

Buy Now

Correct Answer: A

Questions 5

A project manager should formally close out a project when:

A. key project team members are needed to work on other projects.

B. a key stakeholder is satisfied with the project deliverables.

C. the CPI is 1.5 at the midpoint of the project.

D. the project has been terminated unexpectedly.

Buy Now

Correct Answer: D

Questions 6

A project has been delayed due to an ongoing labor dispute. The project sponsor asks the project manager to transfer the risk to complete the project on time. Which of the following is a method of transferring the risk?

A. Delay the project

B. Change the project schedule

C. Outsource the project

D. Hire more resources

Buy Now

Correct Answer: C

Questions 7

A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?

A. Arrow Diagramming Method (ADM)

B. Precedence Diagramming Method (PDM)

C. Critical Path Method (CPM)

D. Critical Chain Method (CCM)

Buy Now

Correct Answer: B

Questions 8

The project is running behind schedule because one of the developers has taken an unscheduled vacation. The project manager informs the developer that any further unauthorized absence will result in removal from the project. Which of the following resolution techniques was used?

A. Forcing

B. Negotiating

C. Avoiding

D. Confronting

Buy Now

Correct Answer: D

Questions 9

Which of the following are characteristics of an approved project charter? (Select Two).

A. Provides the prioritization of work from the stakeholders.

B. Defines the project managers authority.

C. Identifies what the project manager wants to derive from the project.

D. Increases the number of just-in-time processes required to decrease scope creep.

E. Validates the existence of a project.

Buy Now

Correct Answer: BE

Questions 10

A project manager must initially address a performance issue with a project team member. Which of the following communication methods is BEST to use?

A. Formal written communication

B. Informal verbal communication

C. Informal written communication

D. Formal verbal communication

Buy Now

Correct Answer: B

Questions 11

Which of the following is created as part of the closing phase?

A. Quality baseline

B. Cost review

C. Activity estimation

D. Feasibility analysis

Buy Now

Correct Answer: B

Questions 12

Various technologies exist to complete a project, but the project manager is not well versed in these technologies. Which of the following can the project manager initiate to assist with the decision?

A. A Statement of Work (SOW)

B. A project needs assessment

C. A vendor contract

D. A Request for Proposal (RFP)

Buy Now

Correct Answer: D

Questions 13

A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?

A. Distribute details of the change per the communication plan, and implement according to the change control process.

B. Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.

C. Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team members.

D. Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.

Buy Now

Correct Answer: A

Exam Code: JK0-017
Exam Name: CompTIA E2C Project+
Last Update: May 27, 2026
Questions: 402

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2026 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.