Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > CompTIA > CompTIA Certifications > JK0-017 > JK0-017 Online Practice Questions and Answers

JK0-017 Online Practice Questions and Answers

Questions 4

During which of the following process groups is the availability of required resources for the project determined?

A. Executing

B. Monitoring/Controlling

C. Initiating

D. Planning

Buy Now

Correct Answer: D

Questions 5

Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the following should the shared resource be documented?

A. Quality management metrics

B. Work Breakdown Schedule (WBS)

C. Scope statement

D. Risk register

Buy Now

Correct Answer: D

Questions 6

The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?

A. The project will be behind schedule and over-budget.

B. The project will be on schedule but over-budget.

C. The project will be on schedule and on-budget.

D. The project will be behind schedule and on-budget.

Buy Now

Correct Answer: C

Questions 7

Transition plans include which of the following elements?

A. Work Breakdown Structure (WBS)

B. Project warranty

C. Project process reports

D. Earned value calculations

Buy Now

Correct Answer: B

Questions 8

In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project?

A. $150,000

B. $300,000

C. $450,000

D. $600,000

Buy Now

Correct Answer: D

Questions 9

A project manager has decided to reduce the impact of a possible threat. Which of the following risk response strategies BEST describes this action?

A. Avoidance

B. Exploiting

C. Mitigation

D. Acceptance

Buy Now

Correct Answer: C

Questions 10

Before the execution phase begins, who is in control of the project?

A. Project sponsor

B. Program manager

C. Project manager

D. Project coordinator

Buy Now

Correct Answer: C

Questions 11

Pareto charts helps the project manager with which of the following?

A. Determine if a process will be experiencing difficulties.

B. Focus on creative thinking.

C. Explore required future events.

D. Focus on the most critical issues to improve quality.

Buy Now

Correct Answer: D

Questions 12

A project manager is managing the delivery of a project awarded under a fixed-cost contract. The project cost was poorly planned and underestimated, but the projects overall scope and deadline cannot change. Failure to deliver the project is not an option. Which of the following will MOST likely be affected by these circumstances?

A. Earned Value (EV)

B. Quality

C. Change management

D. Resource leveling

Buy Now

Correct Answer: B

Questions 13

A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?

A. Distribute details of the change per the communication plan, and implement according to the change control process.

B. Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.

C. Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team members.

D. Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.

Buy Now

Correct Answer: A

Exam Code: JK0-017
Exam Name: CompTIA E2C Project+
Last Update: Jun 11, 2025
Questions: 402

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2025 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.