Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management
The process of prioritizing risks for further analysis or action is known as:
A. Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.
The following is a network diagram for a project.
The free float for Activity E is how many days?
A. 2
B. 3
C. 5
D. 8
An input to the Control Quality process is:
A. Activity attributes
B. Quality control measurements
C. Enterprise environmental factors
D. Deliverables
Taking out insurance in relation to risk management is called what?
A. Transference
B. Avoidance
C. Exploring
D. Mitigation
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
A. Critical path method
B. Variance analysis
C. Schedule compression
D. Schedule comparison bar charts
Which activity involves ensuring that the composition of a projects configuration items is correct?
A. Configuration Identification
B. Configuration Status Accounting
C. Configuration Verification and Audit
D. Configuration Quality Assurance
In which Process Group are lessons learned documented?
A. Planning
B. Closing
C. Executing
D. Initiating
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
A. Performance organizations
B. Schedule baselines
C. Work performance measurements
D. Change requests
The project governance approach should be described in the:
A. change control plan
B. project scope
C. statement of work
D. project management plan