Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > PMI > PMI Certifications > PMI-RMP > PMI-RMP Online Practice Questions and Answers

PMI-RMP Online Practice Questions and Answers

Questions 4

You are project manager for ABD project. You, with your team, are working on the following activities:

1.

Probabilistic analysis of a project.

2.

Probability of achieving cost and time objectives.

3.

Trends in Qualitative Risk Analysis results.

On which of the following processes are you working on?

A. Plan Risk Management

B. Perform Quantitative Risk Analysis

C. Perform Qualitative Risk Analysis

D. Identify Risks

Buy Now

Correct Answer: B

Questions 5

Mary is the project manager of the HGH Project for her company. She and her project team have agreed that if the vendor is late by more than ten days they will cancel the order and hire the NBG Company to fulfill the order. The NBG Company can guarantee orders within three days, but the costs of their products are significantly more expensive than the current vendor. What type of a response strategy is this?

A. Internal risk management strategy

B. Contingent response strategy

C. External risk response

D. Expert judgment

Buy Now

Correct Answer: B

Questions 6

You are the project manager of RTF project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows causal factors for an effect to be solved. What diagramming technique are you using as a part of the risk identification process?

A. Cause and effect diagrams

B. System or process flow charts

C. Predecessor and successor diagramming

D. Influence diagrams

Buy Now

Correct Answer: A

Questions 7

You work as a project manager for BlueWell Inc. Management has asked you to work with the key project stakeholder to analyze the risk events you have identified in the project. They would like you to analyze the project risks with a goal of improving the project's performance as a whole. What approach can you use to achieve the goal of improving the project's performance through risk analysis with your project stakeholders?

A. Focus on the high-priority risks through qualitative risk analysis

B. Involve the stakeholders for risk identification only in the phases where the project directly affects them

C. Involve subject matter experts in the risk analysis activities

D. Use qualitative risk analysis to quickly assess the probability and impact of risk events

Buy Now

Correct Answer: A

Questions 8

Upon returning from vacation, the risk manager observes during the project status meeting that several activities being accomplished were not in the original plan. What should the risk manager do first?

A. Meet with the project team.

B. Inform management of out-of-scope work.

C. Review activities for new risks.

D. Review the change control log.

Buy Now

Correct Answer: D

Questions 9

Wendy is the project manager of the NNJ project for her company. As part of the variance and trend analysis tool and technique for risk governance she is using earned value management. In this approach, Wendy wants to track and compare the cost and schedule variances. What is the point of this tool and technique in regard to risk?

A. Wendy can determine a true project completion date.

B. Wendy can track the cost and schedule variances.

C. Wendy can review quality performance on baselines.

D. Wendy can forecast deviation of the project cost and schedule for completion targets.

Buy Now

Correct Answer: D

Questions 10

A project is in the planning phase, and the risk manager establishes the risk management for the project. Which success factors should be taken into account by the risk manager to establish a successful risk management process for the project?

A. Organizational commitment, scale risk effort to project, early identification of risks

B. Organizational commitment, scale risk effort required to project, perform quantitative risk analysis

C. Organizational commitment, scale risk effort required to project, integrate with other project management areas

D. Organizational commitment, scale risk effort required to project, use Monte Carlo analysis for risk evaluation

Buy Now

Correct Answer: C

Questions 11

Which of the following best describes the strength of the probability and impact matrix for qualitative risk analysis?

A. It is well-suited to a decision tree analysis.

B. It assists in handling other factors such as urgency and manageability that may partly determine the risk's ranking.

C. It provides expert facilitators for the quantitative risk analysis.

D. It reflects the organization's level of risk appetite.

Buy Now

Correct Answer: B

Questions 12

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

A. Recommend the removal of risks to the project manager to reduce project risk exposure.

B. Advise the client that the project has exhausted contingency.

C. Quantify the risk exposure that exceeds project contingency.

D. Generate reports to assess and communicate the project risk level.

Buy Now

Correct Answer: C

Explanation: The project risk manager should generate reports to assess and communicate the project risk level to stakeholders. This helps in making informed decisions and taking appropriate actions to manage risks effectively. The project risk manager should quantify the risk exposure that exceeds project contingency, as this will help to determine the amount of management reserve needed to cover the potential cost overruns or schedule delays. The project risk manager should also communicate this information to the project manager and other relevant stakeholders, and update the risk management plan accordingly. References: The Standard for Risk Management in Portfolios, Programs, and Projects, page 80; PMBOK Guide, 6th edition, page 407.

Questions 13

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

A. Perform a probability and impact assessment

B. Perform Monte Carlo simulations

C. Perform a sensitivity analysis

D. Perform a risk data quality assessment

Buy Now

Correct Answer: D

Explanation: After gathering cycle time data, the risk manager should perform a risk data quality assessment to ensure the data is accurate, reliable, and relevant for evaluating the current process and the new software. A risk data quality assessment is a technique to evaluate the degree to which the data about risks is useful and accurate for risk management. It involves examining the reliability, credibility, accuracy, and validity of the data collected. A risk data quality assessment can help the risk manager to determine the confidence level of the risk analysis and the quality of the risk responses. Performing a risk data quality assessment is the next logical step after gathering the cycle time data, as it will help to ensure that the data is suitable for further analysis and decision making. References: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 9; A Guide to the Project Management Body of Knowledge (PMBOK Guide) Sixth Edition, page 397.

Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP)
Last Update: Jul 10, 2025
Questions: 670

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2025 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.