Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > PMI > PMI Certifications > PMI-RMP > PMI-RMP Online Practice Questions and Answers

PMI-RMP Online Practice Questions and Answers

Questions 4

You are the project manager for your organization. You are working with your key stakeholders in the qualitative risk analysis process. You understand that there is certain bias towards the risk events in the project that you need to address, manage, and ideally reduce. What solution does the PMBOK recommend to reduce the influence of bias during qualitative risk analysis?

A. Establish the definitions of the levels of probability and impact

B. Provide iterations of risk analysis for true reflection of a risk probability and impact

C. Isolate the stakeholders by project phases to determine their risk bias

D. Involve all stakeholders to vote on the probability and impact of the risk events

Buy Now

Correct Answer: A

Questions 5

Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project. She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely. What risk response has Holly used in this instance?

A. This is the risk mitigation response.

B. This is the avoidance risk response.

C. This is the transference risk response.

D. This is a scope change and not a risk response.

Buy Now

Correct Answer: B

Questions 6

You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?

A. It is a risk that can not be addressed by a risk response.

B. It is a risk that will remain no matter what type of risk response is offered.

C. It is a risk that remains because no risk response is taken.

D. It is a risk that remains after planned risk responses are taken.

Buy Now

Correct Answer: D

Questions 7

Who is the most appropriate person to conduct a risk identification brainstorming session?

A. Facilitator

B. Subject matter expert

C. Project manager

D. Project sponsor

Buy Now

Correct Answer: A

Questions 8

Which analysis method uses stratified sampling without replacement?

A. Latin Hypercube

B. Monte Carlo simulation

C. Impact analysis

D. Linear regression analysis

Buy Now

Correct Answer: A

Questions 9

Given the output from the Monte Carlo simulation, what is the probability of a successful completion within the project budget?

A. 30% probability of meeting project budget

B. 46% probability of meeting project budget

C. 56% probability of meeting project budget

D. 60% probability of meeting project budget

Buy Now

Correct Answer: C

Questions 10

During a company's audit, it is found that no risk management information exists within the lessons learned database. What could the company do to increase the amount of risk management organizational process assets?

A. Require the project manager to record significant risk management information, to provide concrete data in the lessons learned database for future projects.

B. Require the PMO to merge and distribute risk logs to all key stakeholders associated with risk management.

C. Require the project manager to update the project management office (PMO) policy and procedures on an iterative basis to ensure relevancy to current projects.

D. Require the PMO to perform quality audits on all active projects, to ensure alignment with communication industry standards.

Buy Now

Correct Answer: A

Questions 11

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

A. Wait until the weather improves before sending the equipment.

B. Ask the project sponsor to approve shipping the equipment.

C. Proceed with the planned risk response to move the equipment.

D. Request the shipment of the equipment to satisfy the client.

Buy Now

Correct Answer: C

Explanation: The project manager should proceed with the planned risk response to move the equipment, as this is the best way to deal with the weather-related risk that was identified and recorded in the risk register. A risk register is a document that lists all the identified risks, their causes, impacts, probabilities, and responses for a project1. A risk response is a strategy or action that is taken to reduce the negative effects or enhance the positive effects of a risk event2. A risk response should be planned and executed according to the risk management plan, which is a document that describes how risk management activities will be structured and performed on a project3. The risk management plan should also define the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance mechanisms3. Therefore, the project manager should follow the risk management plan and the risk register to implement the planned risk response to move the equipment, as this is the most effective and efficient way to manage the risk and meet the project objectives. Waiting until the weather improves before sending the equipment, asking the project sponsor to approve shipping the equipment, or requesting the shipment of the equipment to satisfy the client are not the best options to deal with the weather-related risk. Waiting until the weather improves may cause further delays and increase the cost and scope of the project, as well as damage the relationship with the client. Asking the project sponsor to approve shipping the equipment may not be necessary or feasible, as the project sponsor may not have the authority or the availability to make such a decision. Requesting the shipment of the equipment to satisfy the client may not be realistic or safe, as the bad weather may pose a threat to the quality and integrity of the equipment, as well as the health and safety of the people involved in the transportation. These options may also deviate from the risk management plan and the risk register, which may create confusion and inconsistency in the risk management process. References: 1, 2, 3.

Questions 12

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

A. Implement the secondary risk response and update the project documents.

B. Conduct meeting with all stakeholder to agree on post impact solutions.

C. Set the corresponding trigger conditions to the secondary risk.

D. Engage the project manager to authorize the secondary risk's response.

E. Update and communicate assessments of the secondary risk's impact.

Buy Now

Correct Answer: AE

Explanation: The risk owner should implement the secondary risk response, as it is now being tolerated, and update the project documents accordingly. They should also update and communicate the assessments of the secondary risk's impact to ensure everyone is aware of the situation.

According to the PMI-RMP Handbook1, the risk owner is responsible for implementing the risk response plan and monitoring the risk and its secondary risks. Therefore, the risk owner should take the following two actions when the secondary risk emerges: Implement the secondary risk response and update the project documents. This action is consistent with the risk response strategy of tolerance, which means accepting the risk and its consequences. The risk owner should execute the planned response for the secondary risk, such as contingency plans or fallback plans, and update the relevant project documents, such as the risk register, the risk report, and the lessons learned register, to reflect the current status and impact of the risk. Update and communicate assessments of the secondary risk's impact. This action is consistent with the risk monitoring and control process, which involves tracking the identified risks, evaluating their impact and probability, and reporting the risk information to the appropriate stakeholders. The risk owner should reassess the secondary risk's impact on the project objectives, such as scope, schedule, cost, and quality, and communicate the results to the project manager and other relevant stakeholders, such as the sponsor, the customer, and the team members. References: PMI-RMP Handbook1 PMBOK Guide, 6th edition, Chapter 11: Project Risk Management2

Questions 13

FILL BLANK

Fill in the blank with an appropriate phrase.

________is the study of how the variation (uncertainty) in the output of a mathematical model can be apportioned, qualitatively or quantitatively, to different sources of variation in the input of a model.

Buy Now

Correct Answer: Sensitivity analysis

Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP)
Last Update: Jul 05, 2026
Questions: 707

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2026 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.