You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen delays that will require your attention. You will need four inputs to the control schedule process. Which of the following documents would not be an input for the control schedule process?
A. Project schedule
B. Work performance information
C. Project management plan
D. Earned value management results
You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?
A. Scope baseline
B. Milestone list
C. Project charter
D. Project Schedule Management Plan
Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods. What can Bonnie create to gain support from the stakeholders in her project?
A. Stakeholder identification tools
B. Expert judgment
C. Stakeholder Analysis Matrix
D. Communications management plan
You are working with your project team to control the project schedule. You will need five inputs to this process throughout your project. Which one of the following is an output of the project schedule control, and NOT an input?
A. Work performance information
B. Project schedule
C. Project management plan
D. Work performance measurements
Donna's project has a budget at completion of $1,987,560 and she is currently 40 percent complete. Her project schedule called for her to be 45 percent complete but there have been some complications in the project. These complications have caused Donna to spend $125,000 more than what the work she has completed is worth. Based on this information what is the cost performance index (CPI) for Donna's project?
A. 86
B. $920,024
C. .90
D. .86
Which of the following techniques is used to perform progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure?
A. Imminent activity management
B. Predecessor-only diagramming
C. Rolling wave planning
D. Decomposition
John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?
A. 0.76
B. 0.85
C. 0.80
D. 0.92
Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.
A. Reports
B. Meetings
C. Diaries
D. Future planning
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project Management process are you working with when you create a new target schedule?
A. Develop schedule
B. Estimate activity durations
C. Control schedule
D. Estimate activity resources
Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.
A. Conflict resolution should focus on issues, not personalities.
B. Conflict is natural and forces a search for alternatives.
C. Openness resolves conflict.
D. Conflict is an individual issue.