Exam2pass
0 items Sign In or Register
  • Home
  • IT Exams
  • Guarantee
  • FAQs
  • Reviews
  • Contact Us
  • Demo
Exam2pass > PMI > PMI Certifications > PMI-SP > PMI-SP Online Practice Questions and Answers

PMI-SP Online Practice Questions and Answers

Questions 4

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?

A. Five days

B. Four days

C. Eleven days

D. Zero

Buy Now

Correct Answer: D

There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float available for Activity G because it is on the critical path.

Questions 5

Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk- adverse with this project. Which of the following methods should Ben avoid to recoup the project time?

A. Crashing

B. Fast tracking

C. Critical chain methodology

D. Adding lead time

Buy Now

Correct Answer: B

Of all the choices, Ben should avoid fast tracking, as it allows complete phases of the project to overlap, and this increases project risks. Management wants to avoid risks, so fast tracking would not be helpful. Fast tracking is a technique for

compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope.

Answer option A is incorrect. Crashing adds people and costs but is relatively safe in regard to risks. Answer option C is incorrect. Critical chain is not a schedule compression technique and would not necessarily help the project get back on

schedule.

Answer option D is incorrect. Lead time, similar to fast tracking, can increase project risks; however, fast tracking is more risky than lead time. Lead time allows individual activities to overlap, while fast tracking allows entire project phases to

overlap.

Questions 6

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

A. It is a term used to describe activities whose effort cannot be directly measured to the project objectives.

B. It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.

C. It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.

D. It is a term used to describe activities that are core project management processes, but not core project activities.

Buy Now

Correct Answer: B

Discrete effort is a term used to describe the work that can be measured and traced to the components in the work packages. It is the actual work to create the project deliverables. Discrete effort refers to the particular work effort that can be

identified and traced as having a direct tie to the final completion of the project- related work breakdown structure components and the deliverables. It is necessary that all the efforts have a specific measurable end product or end result.

Answer options A, D, and C are incorrect.

These are not valid definitions of discrete effort.

Questions 7

You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?

A. Project scope statement

B. Project schedule network diagram

C. Activity list

D. Organizational process assets

Buy Now

Correct Answer: B

Sequence Activities is one of the twenty processes of the Planning Process group. It is the process of identifying and documenting relationships among the project activities. Inputs Following are the inputs to this activity:

Activity list

Activity attributes

Milestone list

Project scope statement

Organizational process assets

Outputs Following are the outputs of the sequence activities process:

Project schedule network diagrams

Project document updates

Questions 8

Kay is the project manager of the QUI Project. This project is done but is also considerably over budget. Kay has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Kay do with the information regarding the schedule delays and cost overruns?

A. Create an entry in the lessons learned documentation and explain her reasoning behind the corrective actions.

B. Create an exceptions report.

C. Create a variance report.

D. File the information as part of the project final report.

Buy Now

Correct Answer: A

When there have been significant corrective action decisions the reasoning behind the decision should be documented in the lessons learned documentation. What is lessons learned documentation? Lessons learned documentation is prepared to contribute to the lessons learned knowledge database of the organization. It includes the causes of issues, the reasoning behind the corrective action chosen, and other types of lessons learned about stakeholder management. Lessons learned are documented so that they become part of the historical database for the project/program and the performing organization. The lessons learned are compiled, formalized, and stored through out the project's/program's duration. Answer option C is incorrect. A variance report may be appropriate but cost and schedule variances are reported differently. Kay could create a cost variance report and a schedule variance report, but not one report for both project attributes. Answer option B is incorrect. An exceptions report is the same as a variance report. Kay would create a separate exceptions report for cost, and another for schedule. Answer option D is incorrect. The information may go into the project final report but it should be included in the project's lessons learned information when it is discovered.

Questions 9

You work as a project manager for BlueWell Inc. You must communicate on a regular basis with all of your project stakeholders. In your project, you have 755 stakeholders. How many communication channels exist in the project?

A. 284,635

B. 570,025

C. 569,270

D. 755

Buy Now

Correct Answer: A

The number of communication channels describes the number of opportunities for stakeholders to communicate amongst themselves and for communication to be broken down. To find the number of communication channels, you can use the formula of N(N-1)/2 where N represents the number of stakeholders. Total number of communication channels = N(N-1)/2 = 755(755-1)/2 = 284,635 Answer option D is incorrect. This is the number of stakeholders. Answer option C is incorrect. 569,270 is not a valid calculation of this formula. Answer option B is incorrect. 570,025 is not a valid calculation of this formula.

Questions 10

You are the project manager for GGY Project. You are working with your project team to record the actual durations for the activities they have completed in the project schedule. Mary, one of your project team members, wants to know why you need to know how long it actually took the project team to complete their assignments as long as the project work is completed. Which of the following is the best response for Mary's query?

A. Actual durations need to be recorded to track process improvement.

B. Actual durations need to be recorded to create the schedule baseline.

C. Actual durations need to be recorded to measure the actual progress of the project.

D. Actual durations need to be recorded to perform quality control on the project management processes.

Buy Now

Correct Answer: C

The best answer is to track actual durations to measure the actual progress of the project. Actual duration is the time, in the calendar units, between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in development or the actual finish date if the schedule activity is complete.

Answer option B is incorrect. The schedule baseline is not created based on actual durations. Answer option A is incorrect. Process improvement is part of the quality management knowledge area, but it is not a reason to track actual

durations.

Answer option D is incorrect. Quality control is the inspection of the project deliverables. It is not concerned with the actual durations of project work. The improvement of the project processes is defined in the Process Improvement Plan.

Questions 11

You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?

A. $566,305

B. $787,504

C. $1,312,504

D. $733,456

Buy Now

Correct Answer: B

The project will need $787,504 more to complete. This formula, the estimate to complete, is estimate at completion minus the actual costs. Here, CPI = EV/AC =(0.40*1,258,456)/525000= 0.95882, and ETC = EAC - AC = (BAC/CPI) - AC =(1,258,456/0.95882) - 525000 = 1,312,504- 525000 = 787,504 The estimate to complete (ETC) is the expected cost needed to complete all the remaining work for a scheduled activity, a group of activities, or the project. ETC helps project managers predict what the final cost of the project will be upon completion. The formula for the ETC is EAC- AC. The EAC is BAC/CPI. Answer option C is incorrect. This is the estimate at completion. Answer option A is incorrect. This is the planned value. Answer option D is incorrect. This is not a valid value based on the current project performance.

Questions 12

You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?

A. Risk management plan

B. Schedule management plan

C. Risk register

D. Activity attributes

Buy Now

Correct Answer: C

The project risks are documented in the risk register - including the probability and impact information. The risk register is an output of the Identify Risks process. Risk register is a document that contains the results of the qualitative risk

analysis, quantitative risk analysis, and risk response planning. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the risk register.

Answer option A is incorrect. The risk management plan addresses that how risks will be identified, monitored, and controlled. Answer option D is incorrect. The activity attributes information is needed, but risks are not part of the activity

attributes.

Answer option B is incorrect. The schedule management plan addresses how the schedule will be created, executed, and controlled.

Questions 13

Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

A. Stakeholders are usually identified through a stakeholder register.

B. Stakeholders are identified by the project team, project sponsor, and management.

C. Stakeholders are identified through the project customers.

D. Stakeholders are usually identified by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.

Buy Now

Correct Answer: D

Stakeholders are interviewed and can help identify other stakeholders that should be included in the project communications.

Answer option B is incorrect. According to the PMBOK, this is not the best answer. Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by it. Answer option C is incorrect. Project customers are

stakeholders.

Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional (PMI-SP)
Last Update: Jun 13, 2025
Questions: 323

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2025 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.