Which of the following would NOT be classified as a threat to a project?
A. A competitor may launch a rival product first thus affecting the expected market share for the product
B. It is possible that the product completes user acceptance testing in a single test cycle rather that the scheduled two
C. A prototype may be damaged in transit
D. A critical meeting could be affected by air travel disruption
Which of the following is used to inform the Project Board of a forecast deviation of stage-level tolerance?
A. Exception Plan
B. Exception Report
C. Off-specification
D. Lessons Report
What must a PRINCE2 project demonstrate?
1.
It must apply the PRINCE2 principles
2.
It must use the recommended techniques
3.
It must use the defined management products
4.
It must meet the minimum requirements for the themes
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
Where can people who join a project after initiation quickly and easily find information about how the project is being managed?
A. Project brief
B. Project initiation documentation
C. Project mandate
D. Project product description
Identify the missing words in the following sentence.
PRINCE2 defines [ ? ] as an uncertain event that would have a positive impact on objectives.
A. a threat
B. a benefit
C. an opportunity
D. a request for change
Which is a minimum requirement for applying the quality theme?
A. To define the project's approach to quality control
B. To undertake independent audits of the project throughout the project
C. To apply the recommended quality review technique
D. To define the project's approach to quality assurance
Which is an objective of the quality review technique?
A. To baseline a product
B. To provide a common understanding of what products a project will create
C. To define the quality methods required within a project
D. To determine the quality responsibilities of a project team
Which is a purpose of quality planning?
A. Define the structure of the project management team
B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
C. Document approval records for those project products that have met their quality criteria
D. Produce the Project Plan with resource and schedule information
What takes place during the Closing a Project process?
A. The post-project benefits reviews are performed
B. Ownership of the project's products is transferred to the customer
C. An End Stage Report is prepared for the final stage
D. The project closure notification is reviewed and approved
Which process is largely about preventing poorly conceived projects from ever being initiated?
A. Starting Up a Project
B. Initiating a Project
C. Closing a Project
D. Directing a Project