Which TWO describe characteristics of a project?

1.

It is a means for introducing change

2.

It is temporary in nature

3.

It involves repeatable operational tasks

4.

It involves little or no uncertainty

A. 1 and 2

B. 2 and 3

C. 3 and 4 D. 1 and 4

Buy Now

Correct Answer: A

Questions 5

Which theme verifies that a project's products are fit for purpose?

A. Business case

B. Organization

C. Quality

D. Progress

Buy Now

Correct Answer: C

http://prince2.wiki/Quality

Questions 6

What theme estimates the cost of delivering the project?

A. Business Case

B. Change

C. Plans

D. Progress

Buy Now

Correct Answer: C

Questions 7

Which is a task of product-based planning?

A. Identify activities and dependencies

B. Write the Project Product Description

C. Prepare the Work Packages

D. Produce Product Status Accounts

Buy Now

Correct Answer: B

Questions 8

What process covers the acceptance and execution of project work by external suppliers?

A. Controlling a Stage

B. Managing a Stage Boundary

C. Managing Product Delivery

D. Directing a Project

Buy Now

Correct Answer: A

Questions 9

When would the Team Manager be required to produce a Checkpoint Report?

A. When a Work Package is being negotiated

B. At the frequency agreed in the Work Package

C. On completion of the quality-checking activities for each product

D. When reviewing how a stage is progressing

Buy Now

Correct Answer: D

Questions 10

Who carries out checks independent of the project to ensure that the processes are in place for quality planning and control?

A. Project Board

B. Project Assurance

C. Quality Assurance

D. Project Support

Buy Now

Correct Answer: C

Questions 11

Which project management team role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?

A. Project Manager

B. Executive

C. Project Assurance

D. Quality Assurance

Buy Now

Correct Answer: C

Questions 12

Which role would have the assurance responsibility of monitoring any risks in the production aspects of the project?

A. Senior User

B. Team Manager

C. Senior Supplier

D. Executive

Buy Now

Correct Answer: C

Questions 13

According to PRINCE2, Which of the following would be used to pay for a request for change and possibly any analysis costs?

A. Contingency

B. Tolerance

C. Change budget

D. Risk budget

Buy Now

Correct Answer: C

Exam Code: PRINCE2-FOUNDATION
Exam Name: PRINCE2 Foundation
Last Update: Jun 11, 2025
Questions: 1158

PDF (Q&A)

$45.99
ADD TO CART

VCE

$49.99
ADD TO CART

PDF + VCE

$59.99
ADD TO CART

Exam2Pass----The Most Reliable Exam Preparation Assistance

There are tens of thousands of certification exam dumps provided on the internet. And how to choose the most reliable one among them is the first problem one certification candidate should face. Exam2Pass provide a shot cut to pass the exam and get the certification. If you need help on any questions or any Exam2Pass exam PDF and VCE simulators, customer support team is ready to help at any time when required.

Home | Guarantee & Policy |  Privacy & Policy |  Terms & Conditions |  How to buy |  FAQs |  About Us |  Contact Us |  Demo |  Reviews

2025 Copyright @ exam2pass.com All trademarks are the property of their respective vendors. We are not associated with any of them.